Method
How to calculate concrete required in cubic yards
Depth is converted from inches to feet. The resulting cubic feet are divided by 27 to obtain cubic yards.
Worked example
Concrete calculator example
A 20 × 12 ft slab at 4 inches deep contains about 2.96 cubic yards before waste.
Change one assumption at a time to see what drives the result. The output is an estimate, not a quote, forecast or recommendation.
Rule
Exact rule used by the concrete calculator
Volume in cubic feet is length times width times depth, with depth converted from inches to feet by dividing by 12. Dividing by 27 converts cubic feet to cubic yards, and the waste factor then multiplies the result. Cost multiplies the yards by the price per yard.
The calculator handles a rectangle of uniform thickness. Footings, thickened edges and uneven subgrades need separate calculations that you add together. It does not specify a mix, reinforcement or thickness, which depend on the load and local requirements.
Step by step
Worked through step by step
A 10 by 10 ft slab 6 inches thick is 50 cubic feet, or 1.85 cubic yards. With a 10% waste allowance the order is 2.04 yards, costing $305.56 at $150 a yard. Ask the supplier about minimum loads, since small orders are often priced differently.
For bagged mix, divide the cubic feet with waste by the yield on the bag label. An 80 lb bag is commonly labeled at about 0.6 cubic feet, so 55 cubic feet is roughly 92 bags.
Pitfalls
Common mistakes with the concrete calculator
- Entering depth in feet when the field expects inches, which makes the volume twelve times too small.
- Assuming the subgrade is perfectly flat. Low spots take extra concrete.
- Forgetting that a thicker edge or footing adds volume.
- Relying on the cost line for a quote. Delivery, pumping and minimum-load fees are separate.
FAQ
Concrete calculator FAQ
Why include a waste allowance?
Spillage, uneven subgrade and ordering increments can make delivered volume exceed geometric volume.
Can this calculate footings?
Yes for rectangular footings; calculate each distinct shape and add the volumes.
Does this specify concrete mix?
No. Strength, reinforcement and mix design require project-specific engineering guidance.
Why divide by 27?
A cubic yard is 3 feet by 3 feet by 3 feet, which is 27 cubic feet.
How many bags of premixed concrete do I need?
Divide the volume in cubic feet, including waste, by the yield printed on the bag. Yields differ by product, so use the label.